Expansion of the LNG terminal on the island of Krk operational

Croatian government
Copyright: Croatian government

The objective of this investment (EUR 25 million allocated from the REPowerEU, total cost of the investment approx.

EUR 40 million) is to improve diversification of Union’s supply of gas and to increase the security of supply of gas to Croatia’s neighbouring Member States.

The expansion will be done by installing an additional regasification module with the capacity of 250,000 m3/h that will be integrated with the existing module on the Floating Storage Regasification Unit (hereinafter: FSRU) vessel “LNG CROATIA” at the Krk LNG terminal.

The Contract for the procurement of the additional regasification module was signed on 14 April 2023 between LNG Hrvatska LLC and Wärtsilä Gas Solutions Norway AS.